Appendix A:
UW-Green Bay Permit-Required Confined Spaces
Confined Space Program
Air Sampling Procedures
Download:
UW-Green Bay Confined Space Entry Program
Appendix A: UW-Green Bay Permit-Required Confined Spaces
Appendix B: UW-Green Bay Confined Space Entry Form
Appendix C: Air Sampling Procedures
Description of permit space |
Department staff entering space |
Sanitary sewers |
No UW-Green Bay staff, outside contractor |
Storm sewers |
Maintenance |
Elevator pits |
Maintenance, outside contractor |
Sump pump pits |
Maintenance, Heat/Chill |
Water irrigation (soccer pump house) |
Heat/Chill, Grounds |
Water filter (PSC) |
Maintenance |
Stage lift pit |
Weidner |
Orchestra pit |
Weidner |
Scenery painting pit (TH) |
COA Theater |
Clay Pit (SA) |
Maintenance |
Communication Pits |
Technical Services |
Boilers # 1,2,3 – Mud drum, Steam drum, Fire box, Stack (Power Plant) |
Heat/Chill |
Boilers # 4,5 – Fire box |
Heat/Chill |
Condensate tank (Power Plant) |
Heat/Chill |
Deairator tank (Power Plant) |
Heat/Chill |
Sump Pump (Power Plant) |
Heat/Chill |
Cooling Tower Flume (Power Plant) |
Heat/Chill |
Electrical Vault (Power Plant) |
Heat/Chill |
MACH Steam Pit |
Heat/Chill |
Sports Center Steam Pit |
Heat/Chill |