The Campus Master Plan
Campus Master Plan
The Plan provides a physical representation of potential campus growth over the next ten years based on goals and objectives identified through an interactive process with the campus community.

Click the thumbnail for larger image and details
Enlargement

Click the thumbnail for larger image and details
Fundamental Framework
The Campus Master Plan contains recommendations about circulation, wayfinding and navigation, campus spaces, and the visitor experience that are important regardless of the potential for growth. These elements, such as the Inner Loop Road, are represented below.

Click the thumbnail for larger image and details
While the Campus Master Plan is based on growth of the campus to 7,500 students, not all elements of the plan are contingent on such growth. Thus, implementation of the plan includes two components: those changes that would be made to address master planning issues regardless of size; those changes that are necessary to support a larger institution.
It is important to recognize that the conditions and opportunities, which have affected timing of the following list of priorities, may change.
Implementation to meet Existing Needs
Year 1-6 priorities:
- Complete southeast segment of the Inner Loop Road between the new Kress Events Center parking lot and the Laboratory Sciences parking lot
- Complete southeast segment of the Inner Loop Road between the new Kress Events Center parking lot and the Laboratory Sciences parking lot
- Start planning a roundabout at the Nicolet Entrance with the City of Green Bay and Brown County
- Develop a roundabout at the intersection of Circle Drive and Sports Center Drive after the completion of the Kress Events Center expansion
- Re-route Circle Drive to the outside perimeter of the Studio Arts parking lot
- Work with the city transit authority to improve bus routes to campus
- Start planning retail development at the northeast corner of the campus
- Start planning non-traditional housing on the southwest corner of campus
Year 7-12 priorities:
- Construct the roundabout at the Nicolet Entrance
- Complete the southwest segment of the Inner Loop Road between the welcome booth and the Laboratory Sciences parking lot
- Alter signage at the Nicolet Entrance
- Develop the retail facilities at the northeast corner of campus housing
Year 13-18 priorities:
- Complete the remaining segments of the Inner Loop Road
- Plan and construct the campus quad/entry. Remove the concourse link between Student Services and Cofrin Library. Create a pedestrian mall with limited vehicle access between the Weidner Center and Theatre Hall
Implementation to meet Campus Growth
Near Term:
- Obtain approval for campus expansion from the Board of Regents
- Based on approval and academic need, construct projects necessary to support new enrollment and staffing; start with expansion of existing buildings where possible and add new space in locations as identified
- Begin parking lot expansion at locations adjacent to new construction using guidelines included in the master plan
- Relocate housing parking lot to periphery of the housing complex
- Identify housing demand and begin construction at new location on existing parking lot
Fundamental Framework Parking
On-campus parking count in the Fundamental Framework plan is increased only in already developing areas of campus such as the student housing village. housing demand and begin construction at new location on existing parking lot
| LOT | EXISTING | TREATMENT | +/- STALLS | TOTAL |
|---|---|---|---|---|
| Weidner Center | 792 Stalls | Reconfigured, footprint decreased | + 0 Stalls | 915 Stalls |
| Weidner Center Valet Lot |
123 Stalls | Removed, stalls combined with Weidner Ctr. Lot | -123 Stalls | 0 Stalls |
| Wood Hall | 552 Stalls | Reconfigured, footprint nearly the same | + 59 Stalls | 611 Stalls |
| Lab Sciences | 631 Stalls | Reconfigured, footprint nearly the same | + 31 Stalls | 662 Stalls |
| Studio Arts | 595 Stalls | Reconfigured | + 47 Stalls | 642 Stalls |
| Cofrin Hall | 447 Stalls | Expanded to east and south | + 80 Stalls | 527 Stalls |
| Kress Center | Does Not Exist | Parking Lot Added | + 485 Stalls | 485 Stalls |
| Shorewood Golf Course | 119 Stalls | To remain as is | + 0 Stalls | 119 Stalls |
| Visitor Parking Campus Entry |
Does Not Exist | Parking Lot Added | + 187 Stalls | 187 Stalls |
| Visitor Parking | 75 Stalls | To remain as is | + 0 Stalls | 75 Stalls |
| Existing Housing | 525 Stalls | Parking Lot Removed | - 525 Stalls | 0 Stalls |
| East Housing Lot | 229 Stalls | Expanded to north and south | + 772 Stalls | 1001 Stalls |
| Apartment | 238 Stalls | Parking Lot Removed | - 238 Stalls | 0 Stalls |
| Overall | 485 to 1,012 Stalls are Sports Center Expansion | 775 Stalls Added | 5101 Stalls |