Safety & Environmental Management

Appendix A:
UW-Green Bay Permit-Required Confined Spaces


Confined Space Program
Air Sampling Procedures

Download:
UW-Green Bay Confined Space Entry Program
Appendix A: UW-Green Bay Permit-Required Confined Spaces
Appendix B: UW-Green Bay Confined Space Entry Form
Appendix C: Air Sampling Procedures

Description of permit space Department staff entering space
Sanitary sewers No UW-Green Bay staff, outside contractor
Storm sewers Maintenance
Elevator pits Maintenance, outside contractor
Sump pump pits Maintenance, Heat/Chill
Water irrigation (soccer pump house) Heat/Chill, Grounds
Water filter (PSC) Maintenance
Stage lift pit Weidner
Orchestra pit Weidner
Scenery painting pit (TH) COA Theater
Clay Pit (SA) Maintenance
Communication Pits Technical Services
Boilers # 1,2,3 – Mud drum, Steam drum, Fire box, Stack (Power Plant) Heat/Chill
Boilers # 4,5 – Fire box Heat/Chill
Condensate tank  (Power Plant) Heat/Chill
Deairator tank (Power Plant) Heat/Chill
Sump Pump (Power Plant) Heat/Chill
Cooling Tower Flume (Power Plant) Heat/Chill
Electrical Vault (Power Plant) Heat/Chill
MACH Steam Pit Heat/Chill
Sports Center Steam Pit Heat/Chill